1031 FInancial Site Redevelopment Assigned Started Completed !
Cucumber testing preliminary breakdown JoshuaApr 5, 2010 9:15 AM
Develop Definitions for site tiers JoshuaMar 10, 2010 5:00 PMMar 10, 2010 5:14 PM
consolidate to Word doc/outline JoshuaMar 12, 2010 12:05 PM
Receive Client Project Approval Client TBDMar 12, 2010 5:14 PM
Finalize Wireframes (prelim) with client for data points Client TBDMar 25, 2010 11:56 AM
Discuss cucumber process with developer JoshuaMar 15, 2010 5:00 PMMar 15, 2010 11:44 AM
review Front-End - CSS and UI tableless designers JoshuaMar 4, 2010 2:55 PM
follow up with Swoontech + source addtional designers? JoshuaMar 2, 2010 5:18 PM
Lunch Meeting with FE Designer JoshuaMar 5, 2010 5:00 PMMar 8, 2010 11:24 AM
reviewed two candidates from Swoontech JoshuaFeb 18, 2010 2:25 PM
Source any additional Designers? JoshuaFeb 25, 2010 5:00 PMMar 1, 2010 12:26 PM
Inteviewed 2 candidates from Swoontech JoshuaFeb 17, 2010 4:23 PM
2nd review with FE Suhail tonight JoshuaMar 2, 2010 7:00 PMMar 2, 2010 10:09 PM
Hold Meeting with FE Designer JoshuaMar 2, 2010 10:58 AM
Phone conversation with Jennifer Isabell JoshuaMar 4, 2010 9:00 AMMar 4, 2010 11:11 PM
Send email to FE Designer w/ pdf collection for review tonight JoshuaMar 2, 2010 5:00 PMMar 2, 2010 5:18 PM
review candidate availability w/ Dev JoshuaFeb 25, 2010 5:00 PMMar 1, 2010 12:26 PM
Review Backup Designers - availabillity JoshuaMar 3, 2010 10:10 PM
Back-End Framework Dev candidate review JoshuaFeb 1, 2010 12:00 AM
review/discover Developer for site JoshuaFeb 2, 2010 1:59 PM
Post CR1 meeting changes Contractor(s)
modify the contact us (Broker/Dealer) design with ordered cells for Scott JoshuaJul 13, 2010 5:07 PM
Create B/D Contact Us page (with link swap @ login) (see today's updated Dropbox/CSS/CR1-2/contact_fa.html) with PPM offering query only to their 'approved' offerings Contractor(s)Jul 19, 2010 5:27 PM
Create a login page that lists(2 col table) queries of login names (from SalesLogix) with entry fields for 'complete' B/D Names. Title page: "B/D Name Entry" Contractor(s)Jul 22, 2010 12:14 PM
CMS Javascript and Semantic SEO improvements Contractor(s)
find/review Javascript developer for work JoshuaJul 16, 2010
requesting estimate on JS improvements to the site JoshuaJul 16, 2010 12:00 AM
submit JS estimate on CMS and SEO improvements Contractor(s)Jul 20, 2010 12:00 AM
submit Javascript dev estimate for CMS and SEO improvements to IREX for approval JoshuaJul 20, 2010 12:20 PM
await approval on the estimate from IREX Client TBD
await client feedback/changes to copy- Thursday??? Client TBD
build into site a CMS field for the company name and add metatag variable that includes '(company name) - (page name from Admin page editing)' - for better SEO Contractor(s)
More Brochure Title: ADD: ..."Cash Investments" - notify client if it doesn't fit JoshuaJun 30, 2010 3:42 PM
Accordions - change state to where no more than one accordion panel remains open at any given time (except when all are closed) - click/expand auto closes prior accordion (similar to Adobe/Spry js) Contractor(s)
side panel accordion (B/D login) Marketing/ add pdf links/pdf image below - refer to CR1-2 pages Contractor(s)
75 % completed
mock up a more visible graphic/link to login on landing page/index.html for B/D - near bottom of content section. JoshuaJul 15, 2010 1:15 PM
follow-up (TBD) with client that a 'slick' pdf upload is needed or not - mentioned in meeting JoshuaJun 30, 2010 4:27 PM
Shrink down all disclaimer font size -1 and move them/confirm to the bottom of page - review Fleet page JoshuaJul 2, 2010 4:30 PM
GIT Versioning setup JoshuaJul 1, 2010 12:00 AM
review mini-manual on Gui admin JoshuaJul 1, 2010 1:37 PM
speak with Scott on Gui and terminal link - mini refresher course JoshuaJun 23, 2010 10:00 AM
Public Section: Design/Content Formatting Joshua
complete content formatting of public pages dropped by Terrapin Design Group JoshuaJun 4, 2010 5:00 PMJun 4, 2010 2:17 PM
complete content formatting of B/D pages dropped by Terrapin Design Group JoshuaJun 7, 2010 5:00 PMJun 7, 2010 12:00 AM
send "Track Record" page (collect files) and pdf notations for chart converstion to TCG JoshuaJun 8, 2010 1:53 PM
Call Kim D. at TCG to follow-up JoshuaJun 8, 2010 1:52 PM
Post 3rd Green-light: Bulleted breakdown of objectives for each phase JoshuaJul 1, 2010 1:35 PM
Patricia suggested meeting setup after Sue's review Client TBDJul 1, 2010 1:35 PM
killed - followed-up with them but never heard back 7/1
Brief Front End Designer on 3rd iteration Project start-up JoshuaMay 19, 2010 4:25 PM
email to Rich JoshuaMay 14, 2010 5:00 PMMay 17, 2010 2:37 PM
TBD - (Internal): detail historical project schedule on client hold status/work requests ? JoshuaJun 9, 2010 12:00 AM
updated project progress chart with new milestones
Brief Back-End Developer on 3rd iteration Project start-up after return from his honeymoon JoshuaMay 26, 2010 5:00 PMMay 26, 2010 5:06 PM
update project flow with dates - print for client JoshuaJun 8, 2010 3:21 PM
bullet point phase 1-4 in writing JoshuaMay 14, 2010 5:00 PMMay 17, 2010 2:37 PM
followup with Patricia/Sue directly JoshuaMay 19, 2010 4:05 PM
submit to client JoshuaMay 19, 2010 4:05 PM
Site Flow/Navigation
update site flow with four tiers of access Feb 23, 2010 9:52 AM
Review in client meeting Client TBDMar 3, 2010 5:00 PMMar 3, 2010 10:03 PM
update w/ INV. Communications section Client TBDMar 10, 2010 5:12 PM
Client to provide page details on INV Communication (provide Word docs) Client TBDMar 10, 2010 5:12 PM
Revise site flows with revisions from client on page omission JoshuaMay 13, 2010 5:00 PMMay 17, 2010 2:38 PM
update user deligation tier JoshuaJun 28, 2010 6:23 PM
revise site flows after second round client revisions (pre CR1) JoshuaMay 24, 2010 11:44 AM
Site Design Work - Site framing/construction Joshua
await client "pause" lift Client TBDApr 1, 2010 2:16 PM
Receive Client Project Approval Client TBDMar 12, 2010 1:36 PM
Recieved tentative green light JoshuaMar 10, 2010 5:17 PM
Create an initial landing page design JoshuaMar 11, 2010 5:00 PMMar 11, 2010 12:00 AM
Revision notes on design ( Internally 2nd Round ) JoshuaApr 5, 2010 5:00 PMApr 5, 2010 2:40 PM
Await final copy from client Client TBDMar 14, 2010 5:00 PMMay 20, 2010 2:23 PM
Await meeting request from client for site review JoshuaMay 13, 2010 2:23 PM
client cancelled but approved IREX site as of work done 5/13/10
Detail changes in BaseCamp PM software JoshuaMay 17, 2010 2:24 PM
review design changes with team JoshuaMay 19, 2010 2:24 PM
request assistance with Laura M. on proofing table data JoshuaJun 25, 2010 5:00 PMJun 25, 2010 10:01 AM
proof charts Joshua
called client on followup to updating charts
inquire with client: review or wait - are the updating? JoshuaJun 30, 2010 4:27 PM
navigation menu: tweak tiers and order of CR1-2 (dropbox) navigation (adjust CMS reordering) JoshuaJul 13, 2010 6:14 PM
Add "1031 Education" section to Marketing group - ask: Scott or myself? JoshuaJun 30, 2010 3:43 PM
fix 1031 Introduction - duplicate vertical bar/image repeat JoshuaJul 1, 2010 1:37 PM
Admin portal Development Joshua
client review Client TBDMay 20, 2010 2:23 PM
revise Admin UI after client review Design TeamMay 28, 2010 1:16 PM
photography of Properties: Joshua
contact Keith/Cindy on need for higher resolution photography than provided on current site JoshuaJun 23, 2010 3:39 PM
Cindy to Email photos of current properties Client TBDJun 23, 2010 3:38 PM
take 3 current properties and crop/format for site JoshuaJun 24, 2010 1:47 PM
upload on admin page JoshuaJul 1, 2010 1:38 PM
Site Hosting & SSL Joshua
Site Hosting ICS
Have ICS discuss details of hosting and quotes ICSMay 21, 2010 12:59 PM
Schedule Meeting (after Scott's return Wed) with Kevin, Noe, Myself, Scott, John S. to go over 3 initial providers JoshuaMay 28, 2010 5:00 PMMay 25, 2010 4:28 PM
await Rail Machine approval on Wed. review/presentation JoshuaJun 1, 2010 5:00 PMJun 2, 2010 1:00 PM
not available for meeting review
provide post-mortem follow up with links to available sites JoshuaJun 2, 2010 5:00 PMJun 2, 2010 12:00 AM
follow up with any questions prior to PTO leave JoshuaJun 8, 2010 9:41 AM
Per follow-up with Debbie S. - schedule Friday morning meeting to review Linode and Rails Machine JoshuaJun 10, 2010 5:00 PMJun 10, 2010 8:44 AM
Contact Kevin on Friday in follow-up JoshuaJun 11, 2010 5:00 PMJun 11, 2010 12:00 AM
Meeting with Hosting companies -June 2nd JoshuaJun 2, 2010 5:00 PMJun 2, 2010 12:00 AM
conference call with Engine Yard JoshuaJun 23, 2010 12:00 AM
Review Debbie S. Email followup JoshuaJun 21, 2010 12:00 AM
Contact Debbie re: Emails/quotes JoshuaJun 21, 2010 12:00 AM
Meet w/ Debbie on outstanding items JoshuaJun 22, 2010 12:00 AM
Contact Scott on post-mortem feedback between 2 hosting companies JoshuaJun 23, 2010 3:36 PM
reach out to Debbie on Scott's comments JoshuaJun 23, 2010 3:40 PM
conference call with Rails Machine - cancelled by host Client TBDJul 2, 2010 4:30 PM
host is back-logged by three weeks
ICS Hosting committee to provide cost breakdowns ICSJul 2, 2010 4:30 PM
evaluate additional host providers? (Kevin) ICSJul 2, 2010 4:30 PM
submit final selections from Hosting Committee to client JoshuaJul 2, 2010 4:30 PM
meet with Debbie on hosting proposal/layout tweaks JoshuaJul 13, 2010 5:08 PM
tabulate hours accrued on finding hosting/SSL options into proposal JoshuaJul 14, 2010 6:06 PM
email Debbie S. on hours JoshuaJul 14, 2010 6:07 PM
(26 hrs for myself, 5 hrs for Scott)
Client meeting on Hosting: Client TBDJul 19, 2010 12:15 PM
Client to authorize Purchase Client TBD
Rails Machine selected
followup: person-to-person support available - Debbie S. Office
Her email: (read/respond) Client TBD
From: Bradley Taylor
Sent: Wednesday, July 21, 2010 4:30 PM
To: Salomoun, Debbie
Subject: Re: Account set up

We'll arrange calls or chats on a per-incident basis if the issue warrants it. We provide very high personal attention with a 15 minute response to urgent (site down) requests and 1 business day on non-urgent. Given the detailed technical nature of our work, email or chat is superior to voice. Although some issues are better handled over the phone. If the contact is non-technical, then we'll just resolve the issue presented in the ticket. We bill hands-on work at $150/hour. Issues that only we can fix (network, hardware, reboots) are always free.

If they are not technical at all and your company won't be working with them anymore, it might be worthwhile for them to engage us with a support retainer.
assist debbie in RM questionaire JoshuaJul 21, 2010 1:56 PM
follow up with Debbie on response JoshuaJul 22, 2010 1:56 PM
requested Debbie to follow up with ICS for a review of RM's retainer policy, needs
await response from ICS' review of retainer policy ICS
follow up: (Joshua) R&T Co. security protocols? JoshuaJul 22, 2010 5:11 PM
L. Wade ran security/verified my Inland Association, recieved clearance from REITs - left VM OfficeJul 22, 2010 12:46 PM
contacted R&T - via phone/email (MaryAnn Hurley) JoshuaJul 22, 2010 12:46 PM
forwarded email to Lynnwood Wade for security OfficeJul 22, 2010 12:46 PM
follow up from VM to Lynnwood Wade JoshuaJul 22, 2010 5:11 PM
800-525-7686 x2575
send email on R&T Co. site security policies and user responsibilities JoshuaJul 19, 2010 12:00 AM
ICS to setup Ruby on Rails site hosting environment for App/web publishing ICS
SSL Security Encription SIte Certificate Joshua
Review preliminary options for site hosting with client - ICS to quote Client TBDMay 20, 2010 12:59 PM
Review SSL Certificate - pricing info JoshuaMay 20, 2010 12:58 PM
SSL request to ICS JoshuaMay 21, 2010 12:59 PM
Client to authorize Purchase Client TBDJul 12, 2010 5:09 PM
purchase of SSL Certificate per client approval ICS
ICS to setup/register SSL certificate to URL ICS
Wireframes - Front-End UI Joshua
await client "pause" lift Client TBDApr 1, 2010 2:16 PM
Update Due Diligence with provided outline from client JoshuaMar 1, 2010 12:25 PM
create B/D view wireframe JoshuaFeb 18, 2010 2:23 PM
create Investor view wireframe JoshuaFeb 18, 2010 2:23 PM
B/D login wireframe JoshuaFeb 10, 2010 1:10 PM
Investor login wireframe JoshuaFeb 10, 2010 1:10 PM
Receive Client Project Approval Client TBDMar 12, 2010 5:14 PM
Update wireframes from Design initiation and client input JoshuaMar 16, 2010 5:00 PMMar 16, 2010 12:00 AM
Meeting with client - delayed ClientsMar 19, 2010 5:00 PMMar 19, 2010 9:04 AM
Update Admin/agent (IREX client) wireframe delegation: 1) B/D JoshuaApr 7, 2010 5:00 PMApr 7, 2010 5:30 PM
update Admin Wireframe to include Inv. Communications pdf uploading JoshuaMay 19, 2010 4:07 PM
Supplements and Amendments wireframe update from client direction Client TBDMay 24, 2010 1:38 PM
Schedule Milestones Joshua
Meet with Catherine about availability Feb 19, 2010 11:12 AM
Propose/schedule tentative milestones JoshuaMar 2, 2010 5:00 PMMar 2, 2010 11:09 AM
review with Designer JoshuaMar 2, 2010 11:09 AM
review with Developer JoshuaMar 3, 2010 5:00 PMMar 3, 2010 10:07 PM
Revise Milestones JoshuaMar 3, 2010 10:08 PM
Meeting with Developer - Lunch JoshuaMar 4, 2010 5:00 PMMar 4, 2010 4:18 PM
update Milestones after full copy provided (Friday May 14?) JoshuaMay 21, 2010 1:01 PM
Basecamp PM Setup JoshuaMar 10, 2010 5:21 PM
Revise scope/milestones JoshuaMar 3, 2010 10:08 PM
Set up dropbox JoshuaMar 9, 2010 1:52 PM
Update Milestones post RFP proposal JoshuaMar 9, 2010 1:13 PM
Setup Initial project Feb 23, 2010 11:02 AM
Send out email invite to Dev and Designer JoshuaMar 9, 2010 5:00 PMMar 10, 2010 5:13 PM
Visual Project Flow for diagram Joshua
needed for clarity on process/timing for meetings
Create Project development flow and review w/ client JoshuaFeb 10, 2010 1:12 PM
Discuss Database approach JoshuaFeb 4, 2010 11:31 AM
Client Review - changes JoshuaFeb 10, 2010 2:09 PM
Revise Milestones JoshuaMar 3, 2010 10:11 PM
Email to Client JoshuaMar 4, 2010 2:06 PM
Database Framework Diagraming Joshua
Meeting with Matt Smith and Scott regarding Sales Logix tech integration/exchange JoshuaApr 8, 2010 5:00 PMApr 8, 2010 9:20 AM
Revere Group on site hosting/database schema JoshuaFeb 18, 2010 3:32 PM
Send data to Developer for review JoshuaFeb 17, 2010 4:23 PM
Phone meeting with Bob Nuber/Revere Group JoshuaFeb 9, 2010 1:36 PM
Build initial tiered diagram from December meetings JoshuaFeb 10, 2010 3:22 PM
Revise with new D.D. section and current appendages to site JoshuaFeb 18, 2010 2:21 PM
Hold Meeting on January updates - detail DD, BD & Investor clarity Client TBDFeb 10, 2010 1:16 PM
Review Saleslogix data points w/ Matt (IREIC) JoshuaFeb 18, 2010 5:00 PMFeb 18, 2010 12:32 PM
Review iManage/ALF process w/ IREX input JoshuaFeb 24, 2010 5:00 PMFeb 24, 2010 5:10 PM
Confirm with ICS/Vern on ALF export initiative JoshuaFeb 24, 2010 9:51 AM
Review iManage with Developer - Jim M. @ CLS JoshuaMar 2, 2010 11:01 AM
Review with client JoshuaMar 2, 2010 1:14 PM
Receive Client Project Approval Client TBDMar 12, 2010 5:14 PM
Review with Matt Smith on Schedule JoshuaMar 11, 2010 1:38 PM
Schedule Review of DB items with Debbie, Matt, Vern and Jim M. (CLS) JoshuaMar 16, 2010 5:00 PMMar 16, 2010 5:43 PM
update flows with new page revisions (omissions) to site (post-ALF meeting) JoshuaMay 26, 2010 5:22 PM
Recieve and review MS Access file for B/D login deligation Client TBDMay 14, 2010 5:00 PMMay 14, 2010 12:00 AM
MS Acess text file export recieved from Kurt instead of requested CSV - review with Scott/db JoshuaMay 26, 2010 5:21 PM
contact M. Smith on CSV SalesLogix deligation vs. MS Access JoshuaMay 27, 2010 5:00 PMMay 27, 2010 10:27 AM
contact Catherine on CSV link - master delegation: MSAccess or SalesLogix JoshuaMay 27, 2010 10:52 AM
contact Scott JoshuaMay 27, 2010 10:52 AM
await confirmation of prop_lkup.csv table has (title) ---identical to ---- ( Client TBDJun 10, 2010 12:16 PM
tables are incomplete on Sales Logix side - follow up on solution with Client JoshuaJun 10, 2010 1:48 PM
follow up with Scott on negating MS Access importance - using Sales Logix data instead JoshuaJun 10, 2010 1:50 PM
Phase II Joshua
Link Sales Logix Offerings Data to ALF Offerings Data (Partnerships) Joshua
awaiting ALF program number (four numeric code) pulled into Sales Logix via ICS .txt export - exported back out to Sales Logix CSV table for RoR import - link ICS
Begin work on adding (ALF) 'Partnership/Fund #' as a drop down into Admin Create/Modify Offering section Contractor(s)Jul 26, 2010 4:52 PM
necissary manual link between Sales Logix and ALF - unless Excell/Access file exists for importing - link does exist - see above
Database exchange - ALF & iManage Joshua
Scott to submit Part 1 of tables (await JDE/Partnership info) Contractor(s)Jul 15, 2010 12:01 PM
follow-up again with Catherine on JDE/Partnerships questions - await response JoshuaJul 22, 2010 12:32 PM
vern to provide CSV files for Scott's review ICSJul 21, 2010 12:00 AM
Scott to import CSV to parse and review possible conflicts Contractor(s)Jul 21, 2010 12:00 AM
discuss with Scott on ALF csv file/structure and TBD client changes JoshuaJul 21, 2010 12:00 AM
follow up with Matt Smith on Sales Logix/ALF link? JoshuaJul 22, 2010 12:35 PM
follow up with Vern G. on Sales Logix/ALF link? JoshuaJul 22, 2010 12:39 PM
left a VM - called back - no known link either by DB or external file - inquired on entry sources - Rachel Crabtree
contact Rachel Crabtree on known SL - ALF link JoshuaJul 21, 2010 4:50 PM
Catherine to setup meeting with her database staff (Jim etc) for known ALF input Client TBD
Scott to submit any possible Part 2 of tables once JDE info is cleared by client Contractor(s)
following: contact Vern regarding a follow-up meeting